Assessment of Causes Affecting Progress Schedules on Construction Investment Projects Funded by State Budget in Hanoi City, Vietnam



Dinh Tuan Hai1, *
1 Faculty of Civil Engineering - Hanoi Architectural University, Km 10, Nguyen Trai Road, Thanh Xuan District, Ha Noi City, Vietnam


Article Metrics

CrossRef Citations:
0
Total Statistics:

Full-Text HTML Views: 271
Abstract HTML Views: 103
PDF Downloads: 100
ePub Downloads: 53
Total Views/Downloads: 527
Unique Statistics:

Full-Text HTML Views: 177
Abstract HTML Views: 74
PDF Downloads: 78
ePub Downloads: 49
Total Views/Downloads: 378



Creative Commons License
© 2023 Dinh Tuan Hai

open-access license: This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International Public License (CC-BY 4.0), a copy of which is available at: https://creativecommons.org/licenses/by/4.0/legalcode. This license permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.

* Address correspondence to this author at the Faculty of Civil Engineering - Hanoi Architectural University, Nguyen Trai Road, Thanh Xuan District, Ha Noi City, Vietnam; Tel: 84 – 985299349; E-mail: haidt@hau.edu.vn


Abstract

Background:

Hanoi, the capital city, is the economic, political, and cultural center of Vietnam. Every year, the City’s Government always spends a large part of the budget on construction investment in order to create a basis for promoting its economic development and improving the residents living standards. However, in the process of implementing investment and construction, many projects were delayed, leading to the failure to achieve the desired investment efficiency.

Objective:

To research and evaluate the causes affecting the progress schedules of construction projects using public investment capital in Hanoi, the authors conducted a survey and used the F-AHP method to analyze data collected data in order to obtain objective and accurate results on the research problem.

Methods:

The causes affecting the progress of construction projects are classified into four groups, including subjective causes from project participants and objective reasons.

Results:

The results show that the causes of the project participants have a stronger influence than the objective causes in which the causes related to the owner and the causes related to the contractor have the highest influence.

Conclusion:

Based on projects ‘ progress schedules, the resources are mobilized, the parties work together to promote the development of the project.

Keywords: Hanoi, Construction, Delays, Projects, Fuzzy, Progress Schedules, Vietnam.